List five attributes or characteristics of a project Manager and briefly discuss any two of the attributes and give reasons why each is important. (6marks).
What are some of the benefits of using a network diagram Briefly discuss two and draw the network diagram below show and calculate the critical path. (10 marks)
Tasks Preceding Time (weeks)
a – 3
b a 7
c b 6
b 9
e c 6
f d 8
g ” e,f” 10